ECE 4th Year Projects
Projets de 4e année de GÉGI

Schedule 2017-2018

Attendance is mandatory. When unable to attend class, arrangement must be made with the instructor prior to the class.

Winter Term (3th year)

Week Date Activities Deliverables
Mar 17 Initial brief (Comp Eng)
14h40-15h10 in Sawyer s5200
Mar 17 Initial brief (Elec Eng Fr)
9h00-9h30 in Sawyer s5200
Mar 17 Initial brief (Elec Eng En)
14h40-15h10 in Sawyer s5200
27 Apr 17 DID-1 PCD due at 23h59

Fall Term (4th year)

Week Date Activities Deliverables
1 7 Sep Introduction
Engineering process
Project work time
2 14 Sep Requirements
Project work time
3 21 Sep Project work time
4 28 Sep Design
Project work time
5 5 Oct Project work time DID-3 SOR due at 23h59
6 12 Oct Project work time
Feedback on SOR
7 19 Oct Scheduling
Exercise
Project work time
Corrections to DID-3 due at 12h40
8 26 Oct Project work time
9 2 Nov Project work time
10 9 Nov Project work time Draft DID-4 PDS due at 23h59
11 16 Nov Effective PDR presentation
Supervisor feedback on Draft PDS
Project work time
12 23 Nov Project work time DID-4 PDS due 23h59
13 30 Nov Preliminary Design Review Presentations DID-5 PDR (presentations schedule)

Winter Term (4th year)

Week Date Activities Deliverables
1 11 Jan Meeting at 12h40 in s5206
2 18 Jan Project work time DID-6 Schedule update due at 13h40
3 25 Jan Project work time
4 1 Feb Project work time
5 8 Feb Progress review meeting (schedule)
Project work time
6 15 Feb Project work time
7 22 Feb Reading week
8 1 Mar Project work time
9 8 Mar Progress review meeting (schedule)
Project work time
Draft DID-7 DDD due at 23h59
10 15 Mar Feedback on draft DID-7 DDD
11 22 Mar Project work time DID-7 DDD due at 23h59
12 29 Mar Final Presentation (guidelines) DID-8 FPP (schedule)
13 5 Apr Final project Demonstration